Question:- What are the two types of progress controls provided by PRINCE2?
Answer:- The two types of progress controls provided by PRINCE2 are – • Time-driven • Event-driven
Question:- Which process triggers the request to deliver a project?
Answer:- Initiating a Project process triggers the request to deliver a project.
Question:- Who is responsible for communicating with stakeholders?
Answer:- Project Board is responsible for communicating with stakeholders.
Question:- Which process can be carried out without using PRINCE2?
Answer:- Managing Product Delivery process can be carried out without using PRINCE2.
Question:- During which process is a Checkpoint Report produced?
Answer:- During Managing Product Delivery process Checkpoint Report is produced.
Question:- Which document contains the planned and actual dates for product approval and hand-over?
Answer:- Product Checklist document contains the planned and actual dates for product approval and hand-over.
Question:- Which PRINCE2 theme addresses the ongoing viability of the different project plans?
Answer:- Progress addresses the ongoing viability of the different project plans.
Question:- Which role maintains the Quality Register?
Answer:- Project support maintains the Quality Register.
Question:- Which role has the responsibility of setting project tolerances?
Answer:- Corporate or Program management has the responsibility of setting project tolerances.
Question:- Which role is responsible for defining and verifying user requirements and expectations?
Answer:- Senior User is responsible for defining and verifying user requirements and expectations.
Question:- What is the purpose of configuration management?
Answer:- The purpose of Configuration Management is to track products.
Question:- Which document defines the acceptance criteria and roles for the project?
Answer:- Project Product Description document defines the acceptance criteria and roles for the project. This is created in the Starting up a Project process and used during the Closing a Project process to help verify that the project has delivered to expectations.
Question:- During which Process is the Work Package status reviewed?
Answer:- During Controlling a Stage process the Work Package status is reviewed.
Question:- Who is responsible for determining the Change Authority and change budget?
Answer:- Executive is responsible for determining the Change Authority and change budget.