Question:- What is the process model of prince2?
Answer:- The process model includes:- • Directing a project(DP) • Starting up a project(SU) • Initiating a project(IP) • Controlling a stage(CS) • Managing a project delivery(MP) • Managing a stage Boundary(SB) • Closing a Project(CP)
Question:- What is directing a project (DP)?
Answer:- It performs:- • Support project • Accept Results • Provides Management Approval
Question:- During which process is the request to approve the next Stage Plan made?
Answer:- During managing a Stage Boundary process the request to approve the next Stage Plan is made.
Question:- Which process allows non-PRINCE2 practices to be integrated into a PRINCE2 project environment when creating products?
Answer:- Managing Product Delivery allows non-PRINCE2 practices to be integrated into a PRINCE2 project environment when creating products.
Question:- Which role is responsible for producing a Product Status Account?
Answer:- Project Support responsible for producing a Product Status Account
Question:- Which role is responsible for drafting the outline Business Case?
Answer:- Executive is responsible for drafting the outline Business Case.
Question:- Which role confirms stage and project progress against agreed tolerances?
Answer:- Project Assurance confirms stage and project progress against agreed tolerances.
Question:- What are the two types of progress controls provided by PRINCE2?
Answer:- The two types of progress controls provided by PRINCE2 are – • Time-driven • Event-driven
Question:- Which process triggers the request to deliver a project?
Answer:- Initiating a Project process triggers the request to deliver a project.
Question:- Who is responsible for communicating with stakeholders?
Answer:- Project Board is responsible for communicating with stakeholders.
Question:- Which process can be carried out without using PRINCE2?
Answer:- Managing Product Delivery process can be carried out without using PRINCE2.
Question:- During which process is a Checkpoint Report produced?
Answer:- During Managing Product Delivery process Checkpoint Report is produced.
Question:- Which document contains the planned and actual dates for product approval and hand-over?
Answer:- Product Checklist document contains the planned and actual dates for product approval and hand-over.
Question:- Which PRINCE2 theme addresses the ongoing viability of the different project plans?
Answer:- Progress addresses the ongoing viability of the different project plans.
